Question: QUESTION 1 0 Chege This is from a Test Corporation makes a product with the following standard costs: Inputs Standard Ouantity / Hours Standard Price

QUESTION 10
Chege This is from a Test Corporation makes a product with the following standard costs:
Inputs
Standard Ouantity/Hours
Standard Price/Rate
Direct Materials
5.6 Kilos
$8.00 per Kilo
Direct Labor
0.25 Hours
$22.00 per hour
Variable Ovehead
0.25 Hour
$2.00 per hour
The company reported the following results concerning this product in October.
Actual Output
Purchase of raw materials
Actual direct labor-hours
Raw materials used in production
Cost of raw materials
Cost of direct labor
Actual variable overhead rate
8.400
units
47,775
2,225
45.500
$294,210
$501.680
$1.80
kilos
hours
kilos
Total
Total
per hour
The materials prioe variance is recognized when materials are purchased. Variable overhead is applied on the basis of direct labor-hours.
Required (Answers should not includes special characters like negative signs or commas. Answers should be in the format 5000 F or 5000 U ):
Compute the materials quantity variance.
Compute the materials price variance.
Total Material Variance
Compute the labor efficiency variance.
Compute the direct labor rate variance.
Total Labor Variance
Compute the variable overhead efficiency variance.
Compute the variable overhead rate variance.
Total Variable Ovemead Variance
QUESTION 1 0 Chege This is from a Test

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!