Question: Question 1 ( 1 0 0 Points ) : A crew of four carpenters and two laborers will be used to build the formwork for
Question Points:
A crew of four carpenters and two laborers will be used to build the formwork for a concrete structure. Work is scheduled for hr per day on Monday through Friday and hr on Saturday. Overtime at a rate of one and onehalf will be paid for all hours over hr per day during the week and double time for all Saturday work. The base wage, taxes, and insurance rates are given in table below.
a Calculate the hourly cost for the crew;
b Calculate the overhead percentage in employing the crew against the basis of "bare cost".
tableItemCarpenter,LaborerBase wage,$$