Question: Question 1 ( 1 0 0 Points ) : A crew of four carpenters and two laborers will be used to build the formwork for

Question 1(100 Points):
A crew of four carpenters and two laborers will be used to build the formwork for a concrete structure. Work is scheduled for 9 hr per day on Monday through Friday and 8 hr on Saturday. Overtime at a rate of one and one-half will be paid for all hours over 8 hr per day during the week and double time for all Saturday work. The base wage, taxes, and insurance rates are given in table below.
a) Calculate the hourly cost for the crew;
b) Calculate the overhead percentage in employing the crew against the basis of "bare cost".
\table[[Item,Carpenter,Laborer],[Base wage,$21.78hr,$15.56hr
Question 1 ( 1 0 0 Points ) : A crew of four

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!