Question: Question 1 1 0 Consider consecutive processes A - B - C , where process A has a capacity of 2 0 units per hour,

Question 1
10
Consider consecutive processes A-B-C, where process A has a capacity of 20 units per hour, process B has a capacity of 25 units per hour, and process C has a capacity of 30 units per hour. Where would an operations manager want any inventory?
in front of process C
Inventory should not exist anywhere.
in front of process A
in front of process B