Question: Question 1 1 1 pts A PERT / CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight

Question 11
1 pts
A PERT/CPM activity has an optimistic time estimate of three days, a most likely time estimate of eight days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is
Learning Objective: 17-08 Analyze networks with probabilistic times.
7
7.5
8
8.5
10