Question: Question 1 1 . 1 You are working for a Civil Engineering Consulting firm as the earthworks Engineer and are required to do the earthworks

Question 1
1.1 You are working for a Civil Engineering Consulting firm as the earthworks Engineer and are required to do the earthworks planning on a road construction over a 1 km section. The volume at the first station A is zero, use the given information below to answer the questions that follow.
The table below provides information of the stations (A-H) and existing ground levels along the centre line of the road. The formation level at station A is 23.5 m above the datum and rises uniformly at a gradient of 2.7%. The stations are situated 50m apart.
Complete the table with corrected volumes and the mass ordinate,
[15]
Show calculations for gradient line values,
[5]
Draw the longitudinal section using the scale of 1:2500 and a vertical scale of 1:250,
[15]
Draw the mass haul diagram using the vertical scale of 1:50 and a horizontal scale of 1:2500 assuming a correction factor of 0.75.
[15]
NB: If your mass haul diagram does not balance, provide reason/s why and propose a solution.
\table[[Station,Ground,Volume],[A,49.8,],[,,+1560],[B,54.3,],[,,+1325],[C,50.4,],[,,+415],[D,44.1,-195],[,,],[E,41.7,-912],[,,-1890],[F,36.7,],[,,-1435],[G,34.5,],[,38.5,],[H,,]]
Table 1.
Question 1 1 . 1 You are working for a Civil

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!