Question: Question 1 1 2 0 pts IN this problem, I have a design that implements cuts and fills. The Black line is the design surface

Question 11
20 pts
IN this problem, I have a design that implements cuts and fills. The Black line is the design surface and the orange line is the natural surface. Assume Stations 0+00 and 5+00 are the tie points where the design goes to zero on cuts and fills. What is the balance of material? Is there more cut or more fill?
Average end area 2.pdf darr
71.48 cu yards cut
73.56 cu yards fill
1929.96 cu yards cut
123.45 Cu Yards fill