Question: QUESTION 1 ( 1 5 ) Tutorial 9 . 1 Make use of the cash data as provided and answer the following: a . Calculate

QUESTION 1(15)
Tutorial 9.1
Make use of the cash data as provided and answer the following:
a. Calculate the estimate at completion (EAC) by making use of the following formula:
EAC=(BACACWPBCWP)11+CV11+SV
\table[[Pask,1,2,3,4,5,6,7,8],[AB,4000,4000,,,2000,,,],[AC,1500,1500,2000,2000,,,,],[AD,5000,,,,,2000,3000,],[BE,,6000,8000,6000,,,,],[BF,,,3000,,2000,2000,2000,2000],[DG,,,4000,1000,,1000,1000,1000],[DH,,,,,,4000,6000,4000]]
Completion Report (after6 weeks)
\table[[TASK,% COMPLETED,ACTUAL COST],[AB,95%,9600],[AC,80%,7800],[AD,75%,6400],[BE,100%,18000],[BF,40%,3500],[DG,60%,5800],[DH,5%,2500]]
% complete is of the whole activity
b. Complete the following table by calculating the answers and by explaining each scenario.
\table[[,BAC,BCWS,BCWP,ACWP,EAC,SV,CV],[1,\table[[20000],[UNITS X],[R10]],\table[[5000],[UNITS]],\table[[5500],[UNITS]],R66000,(a),(b),(c)],[2,R25000,R12000,(d),R11500,(e),10%,(f)],[3***,R30000,R15000,R18000,R18500,(g),R3000,-3%
 QUESTION 1(15) Tutorial 9.1 Make use of the cash data as

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!