Question: Question 1 ( 1 point ) A work element in a project plan requires 2 5 labour hours each by 3 carpenters. The carpenters are

Question 1(1 point)
A work element in a project plan requires 25 labour hours each by 3 carpenters. The carpenters are paid $25 an hour and incur benefit and overhead costs of 70% of their direct labour cost. The total carpenter cost assigned to the work element is
Question 1 options:
over $15,000
between $10,001 and $15,000
less than $5,000
between $5,000 and $10,000
Question 2(1 point)
The allowance for contingencies is usually is the range of
Question 2 options:
1% to 5%
6% to 9%
5% to 10%
7% to 11%
Question 3(1 point)
You have been asked to estimate the costs for a project to build an industrial power plan. Based on historical data, the steam turbine which costs $400,000 accounts for 25% of the total costs of the plant. The expected top down estimated cost for this project would be
Question 3 options:
$1,600,000
$1,800,000
$600,000
$900,000
Question 4(1 point)
The matter of what overhead costs are added and in what amounts is within the project manager's control
Question 4 options:
TrueFalse
Question 5(1 point)
The project manager alone should prepare the cost estimates for the project
Question 5 options:
TrueFalse
Question 6(1 point)
Suppose an individual requires 60 minutes to complete a task on the first attempt, and 48 minutes on the second attempt. The learning rate for this individual is
Question 6 options:
70
80
60
50
Question 7(1 point)
To develop a budget the project manage must work with others to forecast...
Question 7 options:
the cost of the resources
all of these points
when the resources are needed
the resources required
Question 8(1 point)
Estimating the probability and consequences of risks and the impact on project deliverables is
Question 8 options:
qualitative risk analysis
quantitative risk analysis
risk management planning
risk identifiaction
Question 9(1 point)
Which of the following is not a type of quantitative risk analysis
Question 9 options:
FMEA
simulation
expert judgement
decision tree
Question 10(1 point)
The first year's salary cost for a project is $550,000 and wages are forecasted to increase 10% each year. The non-discounted salary cost of a 3 year project is
Question 10 options:
between $1,000,000 and $2,000,000
under $1,000,000
over $3,000,000
between $2,000,001 and $3,000,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!