Question: Question 1 ( 1 point ) At which stage in project management process would the status of the project be assessed regularly in reference to

Question 1(1 point)
At which stage in project management process would the status of the project be assessed regularly in reference to planned activities and their timeline, and if the project is off target, a project manager would take action to bring it back on track?
Controlling and monitoring
Execution
Initiation
Planning
 Question 1(1 point) At which stage in project management process would