Question: Question 1 (1 point) Saved Creat e network diagram, estimate resource requirements, estimate time and cost, develop schedule. What is missing in this sequence? Question

Question 1 (1 point)

Saved

Creat e network diagram, estimate resource requirements, estimate time and cost, develop schedule. What is missing in this sequence?

Question 1 options:

Develop schedule.

Estimate Time and Cost

Develop Scope

Determine critical path

Question 2 (1 point)

Saved

How the work breakdown structure shows dependencies?

Question 2 options:

In work breakdown structure dictionary.

Does not show dependencies.

In Project Plan

In Project Schedule

Question 3 (1 point)

Saved

What input should be used in project initiation processes?

Question 3 options:

Industry standards, list of vendors.

Communication plan, stakeholder management plan.

Historical information, company change control system, industry standards.

List of risks, risk management plan, risk audit

Question 4 (1 point)

Saved

Which of the following activities execute in project closing phase?

Question 4 options:

Complete lessons learned knowledge base.

Ask stakeholder to update lessons learned knowledge base.

Provide functional manager with team members performance evaluation.

Ask team to complete lessons learned knowledge base.

Question 5 (1 point)

Saved

What follows after create process improvement plan?

Question 5 options:

Determine Team

Develop Budget

Develop Schedule

Determine all roles and responsibilities

Question 6 (1 point)

Saved

What processes from monitoring and controlling process group used in scope management process?

Question 6 options:

Verify scope, control scope.

Perform integrated change control.

Control scope, follow processes.

Communicating with stakeholders and create forecasts

Question 7 (1 point)

Saved

A project manager plans communications. What previous task he worked on?

Question 7 options:

Determine quality standards, processes, and metrics.

Prepare procurement documents.

Determine all roles and responsibilities.

Perform risk identification, qualitative and quantitative risk analysis, and risk response planning.

Question 8 (1 point)

Saved

What documents are required for defining project scope?

Question 8 options:

Project charter, requirements documentation, organizational process scope

Project charter, list of requirements, requirements matrix, requirements organizational process assets.

Project charter, requirements documentation, organizational process assets.

Project charter, list of requirements, enterprise environment factors.

Question 9 (1 point)

Saved

What work breakdown structure refers to?

Question 9 options:

Sequentially indexed list of the related work packages.

Sequentially indexed list of project activities.

Indexed list of activities scheduled on the project

Graphical presentation of the project activities

Question 10 (1 point)

Saved

What type of activities project manager applies when validates assumptions, verifies if risk management policies been followed, and assesses the risks?

Question 10 options:

Monitoring and Controlling

Project Audit

Executing

Planning

Question 11 (1 point)

Saved

Which project process group represents the project performance measurement?

Question 11 options:

Executing

Closing

Planning

Monitoring and Controlling

Question 12 (1 point)

Saved

What should be used as an input in project initiation processes?

Question 12 options:

Templates, historical estimates and WBSs, and communications with stakeholders.

Determine what to purchase

Configuration plan.

Stakeholders management strategy.

Question 13 (1 point)

Saved

What would you use during the project initiation?

Question 13 options:

Contracts, list of stakeholders, industry standards, information about company strategic plan.

Communication plan, procurement plan,

WBS and WBS dictionary.

Project Requirements

Question 14 (1 point)

Saved

Project manager completed subdividing project deliverables and project work into smaller, more manageable components.

Description of such work components as work packages and control accounts has been finished too. What should be done next to create network diagram.

Question 14 options:

Estimate Resource Requirement

Determine Team

Determine what to purchase

Create Activity List

Question 15 (1 point)

Saved

What needs to be done before create network diagram?

Question 15 options:

Determine critical path

Estimate time and cost

Create activity list.

Finalize requirements.

Question 16 (1 point)

Saved

Which of the following activities belongs to project monitoring and controlling process group?

Question 16 options:

Determine quality standards, processes, and metrics.

Perform quality control.

Perform quality assurance

Perform quality audit.

Question 17 (1 point)

Saved

What is the output of create work breakdown structure process?

Question 17 options:

WBS and WBS dictionary, scope baseline, project document update.

WBS and WBS dictionary, scope verification, project document update.

WBS and WBS dictionary, scope monitoring and control procedure, scope verification.

WBS and WBS dictionary, scope management plan, project document update.

Question 18 (1 point)

Saved

During what part of the work project manager exchanges with communications most often?

Question 18 options:

Initiation

Closing

Execution

Planning

Question 19 (1 point)

Saved

During which part of a project the most conflicts usually happen and require resolve?

Question 19 options:

Initiation

Closing

Planning

Execution

Question 20 (1 point)

Saved

Which of the following activities execute in project closing phase?

Question 20 options:

Give recognitions and rewards.

Hold final meeting with the team.

Confirm the project scope statement against the project charter.

Update lessons learned.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!