Question: Question 1 ( 1 point ) Saved To crash a project by one time unit, sometimes we need to shorten the duration of multiple activities.

Question 1(1 point)
Saved
To crash a project by one time unit, sometimes we need to shorten the duration of multiple activities.
True
False
 Question 1(1 point) Saved To crash a project by one time