Question: Question 1 (1 point) The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the

Question 1 (1 point) The following table shows
Question 1 (1 point) The following table shows the durations, interdependencies and crash costs per day of the activities of a project. Suppose that the crash time of all activities are zero: Immediate predecessor Activity Duration (days) Crash cost per period $120 2 A 3 B A $150 11 $80 D 5 A $30 E 7 B,C,D $400 What is the slack of activity A? Your