Question: Question 1 (1 point) The following table shows the normal time, crash time, normal cost, and crash cost of an activity. What is the

Question 1 (1 point) The following table shows the normal time, crash

Question 1 (1 point) The following table shows the normal time, crash time, normal cost, and crash cost of an activity. What is the cost of reducing the activity's duration by 3 time units Normal time 25 Crash time 10 Normal cost $160 Note: 1 - Do not include the dollar sign. 2 - Round to 2 decimal places if your answer is not a whole number. Crash cost $300