Question: Question 1 (1 point) Using the above Activity E information, what is activity E's duration? (:3 24 ___ [/) 7 ___/ [/) 5 ___/ (:3

 Question 1 (1 point) Using the above Activity E information, whatis activity E's duration? (":3 24 \\___ [/\") 7 \\___/ [/\") 5\\___/ (":3 12 \\___ Question 2 (1 point) Saved l / 2"Ea. Using the above Network Diagram of activities, which activities are inParallel? '3; B&C FjAsa \\._ _. Question 4 (1 point] Given the

Question 1 (1 point) Using the above Activity E information, what is activity E's duration? (":3 24 \\___ [/\") 7 \\___/ [/\") 5 \\___/ (":3 12 \\___ Question 2 (1 point) Saved l / 2" Ea. Using the above Network Diagram of activities, which activities are in Parallel? '3; B&C FjAsa \\._ _. Question 4 (1 point] Given the above network, what is the early start for Activity C (using the PMI numbering convention)? ('3. 3 x J ("HS \\_2' ("1. 4 \\1__'} (\"J 9 Question 5 (1 point) To calculate the early finish of each activity, you use: Backward pass Forward pass Gantt chart Total float Question 6 (1 point) A Gantt Chart is bar graph, listing of activities with a corresponding bar. The length of the bar is: The duration The start date The end date The slackQuestion 7 (1 point] @v Given the above Network Diagram, you crash Activities C, D and E by one day each. The project duration is: ("Tn Shortened by 3 days \\___/ (\""3 Shortened by 2 days \\___/ if\": Unchanged \\___/ (""3 Shortened by 1 day \\___/

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!