Question: Question 1 1 _ pts What is the name given to a point where process flows diverge? Group of answer choices A . gateway B
Question pts
What is the name given to a point where process flows diverge?
Group of answer choices
A gateway
B join gateway
C split gateway
D process flows do not diverge.
Flag this Question
Question pts
Consider the following process:
As soon as the company receives equipment from the supplier, the supervisor inspects for possible defects on the equipment. This may result in the following three options:
The equipment has no defects, and the company agrees to the renting agreement.
The equipment has minor defects, and the company requests repairs from the supplier.
The equipment has major defects, and the company refuses to rent it
How many possible outcomes are there in the above process?
Group of answer choices
A
B
C
D
Flag this Question
Question pts
When do we use an AND split gateway?
Group of answer choices
A When the outgoing tasks do not need to be mutually exclusive.
B When the outgoing tasks need to be mutually exclusive.
C When the tasks can be done concurrently.
D When the tasks have different outcomes.
Flag this Question
Question pts
Consider the following process:
As soon as the company receives equipment from the supplier, the supervisor inspects for possible defects on the equipment. This may result in the following three options:
The equipment has no defects, and the company agrees to the renting agreement.
The equipment has minor defects, and the company requests repairs from the supplier.
The equipment has major defects, and the company refuses to rent it
Which gateway can be used when modelling these processes?
Group of answer choices
A processing gateway.
B exclusive split.
C and split
D inclusive split
Flag this Question
Question pts
Consider the following process:
As soon as the company receives equipment from the supplier, the supervisor inspects for possible defects on the equipment. This may result in the following three options:
The equipment has no defects, and the company agrees to the renting agreement.
The equipment has minor defects, and the company requests for repairs from the supplier.
The equipment has major defects, and the company refuses to rent it
For the above process, what could be the start event?
Group of answer choices
A Check equipment for defects.
B Equipment received.
C Are there defects on the equipment?
D Check equipment for operating specifications
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock