Question: Question 1) (10 marks) Considering a building project, a project manager has determined that some tasks will be needed to carry out the project. Using

Question 1) (10 marks) Considering a building
Question 1) (10 marks) Considering a building project, a project manager has determined that some tasks will be needed to carry out the project. Using the PERT the following estimates as shown in the table. Task Durations (days) Immediate Predecessors Pessimistic Estimate 36 32 B Optimistic Estimate 28 22 26 14 32 40 Most Likely Estimate 32 28 36 46 A D 16 B E 32 B 18 32 74 24 F B 52 16 G 12 D H 16 26 I 42 26 12 20 34 16 E,G E. G CF J 30 Based on the above task list, answer the following questions: 1. Draw the network representing the project? (3 marks) 2. What is the shortest time to complete the project? (3 marks) 3. What is the probability of completing the project in 100 weeks? (2 marks) 4. Find the slacks for each activity? (2 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!