Question: Question 1: (10 points) You do have six projects under consideration, formulate an integer linear programing model to help you choose between six different projects

Question 1: (10 points) You do have six projects

Question 1: (10 points) You do have six projects under consideration, formulate an integer linear programing model to help you choose between six different projects to maximize the total payoff based on the given constraints. - You have 14 hours of labor available. - Can work on at most 3 projects. - If you work on project 4 , you need to work on project 6 and vice versa. - You can work on project 3 or project 5 , but not both at the same time