Question: QUESTION 1 10 points You have collected the data for an oncoming project. The time is in days and the project direct costs are given
QUESTION 1 10 points You have collected the data for an oncoming project. The time is in days and the project direct costs are given below. The Indirect costs for the project are determined on a daily duration basis. The first 12 days will have an indirect cost of $40/day, and every day over 12 days a cost of $60 days Activity immedin Predecessor Normal Time Crash Time Normal CostDirect Crash Cost/Direct A None 3 2 300 400 5 3 3 100 none A 2 1 200 350 D B, C 3 2 400 600 E D 2 500 900 E 3 3 200 non F 2 2. 100 (Note: (1) You can write only the expression with the actual numbers(2) if you have to make an assumption, explain it) A. How long will the project last? B. What is the total cost of the project? C. How much would it cost to finish the project in 14 days? For the toolbar, press ALT F10 or ALTN-510 (Mad BTW & Paragraph Arla 10pt I XUQ 5 MOO 1 none HI w 211 2 Swand Cik mand Sandtok Sowell
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
