Question: Question 1 (15 marks) The project information for the custom order project of the Air Control Company is presented here. a) Draw a project network
Question 1 (15 marks) The project information for the custom order project of the Air Control Company is presented here. a) Draw a project network for this project. (3 marks) b) Compute the early and late activity times and the slack times. (6 marks) c) Identify the critical path.(2 marks) d) Using the information, Create a Gantt Chart (4 marks) ID Description Predecessor Time A Order review None 2 B Order standard parts A 4 C Produce standard parts A 10 D Design custom parts A 14 E Software development A 18 F Manufacture custom hardware C, D 16 G Assemble B, F 10 H Test E, G 6