Question: Question 1 (15 marks) The project information for the custom order project of the Air Control Company is presented here. a) Draw a project network

Question 1 (15 marks) The project information for the custom order project of the Air Control Company is presented here. a) Draw a project network for this project. (3 marks) b) Compute the early and late activity times and the slack times. (6 marks) c) Identify the critical path.(2 marks) d) Using the information, Create a Gantt Chart (4 marks) ID Description Predecessor Time A Order review None 2 B Order standard parts A 4 C Produce standard parts A 10 D Design custom parts A 14 E Software development A 18 F Manufacture custom hardware C, D 16 G Assemble B, F 10 H Test E, G 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!