Question: Question 1 ( 2 0 marks ) 1 . 1 Assume that you are one of the hired project managers at the GGD Innovation Hub.

Question 1
(20 marks)
1.1 Assume that you are one of the hired project managers at the GGD Innovation Hub. Draw an activity on node diagram (AON) for one of the projects you are currently heading.
(8)
\table[[Activity,Preceding Activity,Duration (Days)],[A,-,9],[B,A,12],[C,B,6],[D,B,15],[E,C,D,3],[F,E,6],[G,E,12],[H,F,G,9]]
1.2 Identify all paths through the network diagram.
(8)
1.3 Identify the critical path on the network.