A project is running four weeks behind schedule but the Schedule and Costing Plan has not been updated to reflect this. Which of the following actions is most likely to occur?
Project will continue on as is until the next Project Gate review where this problem will be discovered and acted upon
PM will be punished for failing to keep the project updated
PM will need to replan remaining work
PM will have to crash the schedule to get back to the original project schedule and costing plan