Question: Question 1 2 ( 1 point ) Saved Listen Which of the following is not an effective way _ of dealing with a production constraint

Question 12(1 point)
Saved
Listen
Which of the following is not an effective way_of dealing with a production constraint (i.e., bottleneck)?
Increase work schedules and pay overtime rates to workers assigned to the bottleneck area.
Pay overtime to workers assigned to workstations located after the bottlen the production process.
None of these.
Reduce the number of defective units that are produced at the bottleneck
Subcontract work that would otherwise require use of the bottleneck res