Question: Question 1 2 ( 2 points ) Listen According to the triple constraint, projects are bound by several competing constraints which include: cost , scope,
Question points
Listen
According to the triple constraint, projects are bound by several competing constraints which include:
cost scope, time
people, materials, schedules
leadership, administrators, clinicians
specifications, standards, contracts
none of the above