Question: Question 1 2 ( 3 points ) Saved Estimate at completion ( EAC ) is a periodic evaluation of: a ) The cost of work
Question points
Saved
Estimate at completion EAC is a periodic evaluation of:
a The cost of work completed.
b The value of work performed.
c The anticipated total cost at project completion.
d What it will cost to finish the job.