Question: QUESTION 1 / 2 5 MARKSI ( a ) Based on the information in Table 1 , what is the expected length to finish the

QUESTION 1/25 MARKSI
(a)
Based on the information in Table 1, what is the expected length to finish the project?
Draw a complete of the precedence diagram.
[10 Marks)
Table 1: Assembly project
(538
EP - UNITEN - Goog...
Activity
1
2
3
4
5
6
7
Time (hours)
6
7.2.
5
6
4.5
7.7
4
Immediate predecessors
-
1
2,3
3,4
4
5,6
(b) Calculate each path's total activity time based on Table 1.
[6 Marks]
(c) Draw a complete Gantt chart for the project.