Question: Question 1 2 ( 5 points ) You are project manager of a construction roject. One of the team members come to you with the
Question points
You are project manager of a construction roject. One of the team members come to you with the idea which involves a little extra work but will resut in less cost. What will be the BEST way for you to do
a Do costbenefit analysis and then make sure to inform sponsor about the project scope change
b Refuse to consider the change because it will affect the baseline.
c Decline to make changes until a change request is made and change control is performed
d Tell the team to make change because it will result in low cost