Question: Question 1 . ( 2 7 pts ) Consider the following system with 7 processes. Process Processing Time ( minute / job ) Number of

Question 1.(27 pts) Consider the following system with 7 processes.
Process Processing Time (minute/job) Number of workers
15 minutes 1
25 minutes 1312 minutes 2
415 minutes 2
53 minutes 1
620 minutes 3
75 minutes 1
(a)[3pts] Determine:
the critical path:
length of the critical path:
theoretical flow time (TFT):
(b)[4pts] As an OM business process reengineering expert, you can automate any of processes 2,3,4,5,6(but not processes 1 or 7) to reduce the processing time. Answer parts (i) and (ii) independently based on the current system. Your answer should be specific, and in the form: reduce the processing time for process X1 by Y1 minutes, and process X2 by Y2 minutes, etc.
(i) Explain how you can reduce the theoretical flow time (TFT) by exactly 2 minutes (from the current time in part (a))
(ii) Explain how you can reduce the theoretical flow time (TFT) by exactly 3 minutes (from the current time in part (a))
(c)[12pts] Complete the resource utilization table based on the current system and answer the following questions:
Resource unit load unit cap # units total process cap utilization
(min/job)(job/hr)
1
2
3
4
5
6
7
Identify the process capacity (throughput)(jobs/hr) and the bottleneck resource(s).
(d)[8pts] To be able to produce a minimum of 4 per hour, how many workers are needed for each process? Please complete the following table to answer this question.
Resource unit load unit cap # units total process cap utilization
(min/job)(job/hr)
1
2
3
4
5
6
7
Identify the new bottleneck and the new process capacity
 Question 1.(27 pts) Consider the following system with 7 processes. Process

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!