Question: Question 1 . ( 2 7 pts ) Consider the following system with 7 processes. Process Processing Time ( minute / job ) Number of
Question pts Consider the following system with processes.
Process Processing Time minutejob Number of workers
minutes
minutes minutes
minutes
minutes
minutes
minutes
apts Determine:
the critical path:
length of the critical path:
theoretical flow time TFT:
bpts As an OM business process reengineering expert, you can automate any of processes but not processes or to reduce the processing time. Answer parts i and ii independently based on the current system. Your answer should be specific, and in the form: reduce the processing time for process X by Y minutes, and process X by Y minutes, etc.
i Explain how you can reduce the theoretical flow time TFT by exactly minutes from the current time in part a
ii Explain how you can reduce the theoretical flow time TFT by exactly minutes from the current time in part a
cpts Complete the resource utilization table based on the current system and answer the following questions:
Resource unit load unit cap # units total process cap utilization
minjobjobhr
Identify the process capacity throughputjobshr and the bottleneck resources
dpts To be able to produce a minimum of per hour, how many workers are needed for each process? Please complete the following table to answer this question.
Resource unit load unit cap # units total process cap utilization
minjobjobhr
Identify the new bottleneck and the new process capacity
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock