Question: QUESTION 1 (20 Marks) You are the project manager for your company's MCP project. You are collaborating with your project team and business analyst to

QUESTION 1 (20 Marks)

You are the project manager for your company's MCP project. You are collaborating with your project team and business analyst to choose the most effective method for gathering requirements from project stakeholders. The stakeholders for this project are spread across West Africa, but you want to include everyone in the requirements gathering process. There is some concern that, because your group is so dispersed, it will be difficult to gather the required information effectively.

  1. Complete the following table to identify the characteristics of each technique and how it may, or may not, be helpful in this project.

Group Creativity

Technique

Characteristics

MCP Project Benefit

Brainstorming

Nominal Group Technique

Delphi Technique

Idea/mind mapping

Affinity diagram

  1. You want the stakeholders to vote on the main project needs because your stakeholder group is so big. Even if there isn't a majority in favour of the requirements you choose, you'll still utilize the plurality approach to rank them in order of importance. Describe in detail what is the plurality method and how risky is it for project requirements?
  2. You are now prepared to build the requirements management strategy now that the MCP project has established the project's needs. The project requirements will be managed as part of the project according to the requirements management plan. What component of the requirements management plan is responsible for recording and why is this components needed in maintaining control over the physical attributes of the project's product?

QUESTION 2 (20 Marks)

The MindGineer Project for your organization has been assigned to you to oversee as the project manager. A completion budget of RM 1,500,000 and a 18-month timeline are set forth for this project. The project has been ongoing for some time, and it is currently 30% finished, even though you were expected to guarantee 35% completion at this point. Your project continued to be delayed and has already cost RM 485,230 as a result of the unforeseen mistakes.

  1. Given the above information, complete the following table of earned value management formulas:

Name of Formula

Formula

Formula Result

Actual Cost (AC)

Planned Value

Earned Value

Cost Variance

Schedule Variance

Cost Performance Index

Schedule Performance Index

Estimate at Completion

Estimate to Complete

To-Complete Performance Index (BAC)

To Complete Performance Index (EAC)

Variance at Completion

  1. Another project manager who has been assisting you has created an optimistic estimate of RM 10,450, a most likely estimate of RM 22,300, and a pessimistic estimate of RM 36,650 for a portion of this project. What is the three-point estimate in this scenario?
  2. You are currently assisting Datuk Darryl, the project manager for your client, in setting up the project management process of this project. Draw the project management life cycle components for Datuk Darryl to recognize the entire project flow.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!