Question 1) On the tab labeled CPM Network , you will find a skeleton AON network....
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Question 1) On the tab labeled CPM Network , you will find a skeleton AON network. The layout includes the activities required to complete the project. Based on the list of activities and predecessors on the CPM Calculation tab, enter the arcs (lines) to connect the activities. In the model you will note I left a single arc (line) for you. You may copy/paste this as many times as required to assemble your model. You can adjust the slope and length of the line as required by clicking your mouse on the line itself. Do not change any other formatting in the CPM Network tab, just enter the arcs. In the network model I have provided on the CPM Network tab, what do the lines you entered represent? Question 2) On the tab labeled CPM Calculation you will find a matrix where I have listed the activities for the project, the Predecessors, and the Days Required (duration) for each task as required. What is the definition of a predecessor? Question 3) On the tab labeled CPM Calculation you will find a matrix where I have started the computation to find the critical path for the project by calculating the early start/finish as part of the Forward Pass process. Make the entries in the spreadsheet on the CPM Calculation sheet to complete the Forward Pass. What is the earliest time the project can be completed (# of days)? Please note the spreadsheet is not set up with formulas for calculations; you must manually complete these calculations and enter the appropriate values in the spreadsheet. Question 4) After you have completed the Forward Pass, work backwards to complete the Backward Pass process. Make the entries in the spreadsheet on the CPM Calculation sheet to complete the Backward Pass. Please note the spreadsheet is not set up with formulas for calculations; you must manually complete these calculations and enter the appropriate values in the spreadsheet Question 5) After completing Questions 3 and 4, go back to the CPM Calculation tab and complete the Slack column. In the Critical Path column, put a Y in the cells that correspond to the activities that are on the critical path. In your response to this question here on this page, state the activities that are on the critical path and how you made the determination of the activities on the critical path. A 0 4 4 B C E D F 4 G 2 H 2 LEGEND: ES Early Start Time EF Early Finish Time LS Late Start Time LF Late Finish Time Duration Time or f Activity 1 2 J 1 A B C E D F G B H Activity AB с D E F G H I J Description Design Ordr/Rec Materials Construct Frame Prepare Engine Prepare Avionics Cover Frame Install Engine Paint Install Avionics Test Predecessors None A B B B C E, F F D, G, H I Days Req d 4 5 8 6 5 4 2 2 2 1 Forward Pass EST EFT 0 4 Backwards Pass LST LFT Slack Critical Path? Question 1) On the tab labeled CPM Network , you will find a skeleton AON network. The layout includes the activities required to complete the project. Based on the list of activities and predecessors on the CPM Calculation tab, enter the arcs (lines) to connect the activities. In the model you will note I left a single arc (line) for you. You may copy/paste this as many times as required to assemble your model. You can adjust the slope and length of the line as required by clicking your mouse on the line itself. Do not change any other formatting in the CPM Network tab, just enter the arcs. In the network model I have provided on the CPM Network tab, what do the lines you entered represent? Question 2) On the tab labeled CPM Calculation you will find a matrix where I have listed the activities for the project, the Predecessors, and the Days Required (duration) for each task as required. What is the definition of a predecessor? Question 3) On the tab labeled CPM Calculation you will find a matrix where I have started the computation to find the critical path for the project by calculating the early start/finish as part of the Forward Pass process. Make the entries in the spreadsheet on the CPM Calculation sheet to complete the Forward Pass. What is the earliest time the project can be completed (# of days)? Please note the spreadsheet is not set up with formulas for calculations; you must manually complete these calculations and enter the appropriate values in the spreadsheet. Question 4) After you have completed the Forward Pass, work backwards to complete the Backward Pass process. Make the entries in the spreadsheet on the CPM Calculation sheet to complete the Backward Pass. Please note the spreadsheet is not set up with formulas for calculations; you must manually complete these calculations and enter the appropriate values in the spreadsheet Question 5) After completing Questions 3 and 4, go back to the CPM Calculation tab and complete the Slack column. In the Critical Path column, put a Y in the cells that correspond to the activities that are on the critical path. In your response to this question here on this page, state the activities that are on the critical path and how you made the determination of the activities on the critical path. A 0 4 4 B C E D F 4 G 2 H 2 LEGEND: ES Early Start Time EF Early Finish Time LS Late Start Time LF Late Finish Time Duration Time or f Activity 1 2 J 1 A B C E D F G B H Activity AB с D E F G H I J Description Design Ordr/Rec Materials Construct Frame Prepare Engine Prepare Avionics Cover Frame Install Engine Paint Install Avionics Test Predecessors None A B B B C E, F F D, G, H I Days Req d 4 5 8 6 5 4 2 2 2 1 Forward Pass EST EFT 0 4 Backwards Pass LST LFT Slack Critical Path?
Expert Answer:
Related Book For
Financial and Managerial Accounting the basis for business decisions
ISBN: 978-0078025778
17th edition
Authors: Jan Williams, Susan Haka, Mark Bettner, Joseph Carcello
Posted Date:
Students also viewed these accounting questions
-
Beta of firm and idiosyncratic risk [10 points] The stock price of Beavers, a logging firm, tends to increase by 50% on average when the economy is booming. When the economy is weak, it goes down by...
-
The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not...
-
Which of the following is NOT a source of capital for start-up businesses? a. Personal Savings b. Family and Friends c. Sales revenue O d. Bank Loans
-
Find r(t) and v(t) given a(t) and the initial velocity and position. a(t) = (t, 4), v(0) = (3,-2), r(0) = (0,0)
-
Go through your daily newspaper and identify: (a) Seven or eight news items of an international economic character; (b) The importance or effect of each of these problems on the U.S. economy; (c) The...
-
A 0.326 8-g unknown containing Pb(CH 3 CHOHCO 2 ) 2 (lead lactate, FM 385.3) plus inert material was electrolyzed to produce 0.111 1 g of PbO2 (FM 239.2). Was the PbO 2 deposited at the anode or at...
-
Frahm tachometers are particularly useful to measure the speeds of engines whose rotating shafts are not easily accessible. When the tachometer is placed on the frame of a running engine, the...
-
(Inventory Errors) The net income per books of Adamson Company was determined without knowledge of the errors indicated below. Prepare a work sheet to show the adjusted net income figure for each of...
-
Apply the GLOBE leadership dimensions to Jack Ma and explain his leadership style. What can we learn? GLOBE Leadership Dimensions: Autonomous Leadership Charismatic/Value-based Leadership Humane...
-
The Crazy Eddie fraud may appear smaller and gentler than the massive billion-dollar frauds exposed in recent times, such as Bernie Madoffs Ponzi scheme, frauds in the subprime mortgage market, the...
-
On January 1, 2024, Wright Transport sold four school buses to the Elmira School District. In exchange for the buses, Wright received a note requiring payment of $516,000 by Elmira on December 31,...
-
Why is it necessary to treat previous process cost as a separate element of cost in a process costing system?
-
What are the four primary elements of the database approach?
-
How would you manage an employee who misses performance goals?
-
What is the flat-file model?
-
(a) Describe the distinguishing characteristics of production systems where: (i) job costing techniques would be used, and (ii) process costing techniques would be used. (b) Job costing produces more...
-
1. The following problems deal with translating from C to MIPS. Assume that variables g, h, i, and j are given and implemented as 32-bit integers in a C program. You can assume that the values have...
-
Describe a job you have had in the past or a job you are very familiar with. Indicate the negative aspects of the job and how it could be improved with current human resource management techniques.
-
Exhibit 259 identifies balanced scorecard performance measures. Review this exhibit and identify two measures from the customer perspective category that in the short run might be in conflict with...
-
An analysis of the income statement and the balance sheet accounts of Marys Fashions at December 31, 2015, provides the following information: Income statement items: Gain on Sales of Marketable...
-
Explain why it is necessary to distinguish between cash bud get estimates and operating budget estimates.
-
A suspension system is being designed for a \(1000 \mathrm{~kg}\) vehicle. A first model of the system used in the design process is a spring of stiffness \(k\) in parallel with a viscous damper of...
-
Determine the steady-state amplitude of motion of the \(5-\mathrm{kg}\) block. The coefficient of friction between the block and surface is 0.11 . (See Figure P4.73.) y(t) 3.2 x 10 sin 220 m 1 10 N/m...
-
A \(1000 \mathrm{~kg}\) turbomachine has a rotating unbalance of \(0.1 \mathrm{~kg} \cdot \mathrm{m}\). The machine operates at speeds between 500 and \(750 \mathrm{rpm}\). What is the maximum...
Study smarter with the SolutionInn App