Question: QUESTION 1 ( 3 0 Points ) Solve the network for the basic scheduling information. For each activity, show the computed values of early start
QUESTION Points Solve the network for the basic scheduling information.
For each activity, show the computed values of early start ES early finish EF late start
LS late finish LF and total float.
Indicate the critical path.
Activity D has days of free float
Activity G has days of free float
Use this legend for the activity representation: