Question 1)(30 points)
\table[[Symbol,Immediate Predecessors,Time estimat],[,-,15],[A,-,25],[B,-,],[C,A,3],[D,C,7],[E,,1],[F,B,5],[G,D,F,2],[H,D,F,4],[I,E,F,10],[J,,8],[K,G.J,]]
a.(7.5 points) Draw the AOA network for this project
b.(7.5 points) Calculate the total slacks and interpret the meaning; calculate critical path and interpret the meaning.
c.(15 points) Suppose that activities D, E, F are subject to uncertainty and that only the following time estimates are available. Calculate the probability that the project will be completed in days, for d=52,53,56 plot the probability as a function of d
\table[[Activity,a,m,b],[D,2,4,5],[E,5,6,9],[F,1,3,4]]
Question 1 ) ( 3 0 points ) \ table [ [ Symbol ,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!