Question: [ Question 1 3 1 6 ] A factory owner is going to construct a sales building with a connecting power plant and fire tank.

[Question 1316] A factory owner is going to construct a sales building with a
connecting power plant and fire tank. The activities, activity description, estimated
durations, and pre-requirements are given in the following table.
13. Identify the critical path.
a) A B F G
b) A B F H
c) A B E G - H
d) A C E G H
e) None of the above.
14. What is the project duration for the above network?
a)18
b)20
c)22
d)24
e) None of the above
15. Find slack for the activity C
a)0
b)1
c)2
d)3
e)4
16. Find slack for the activity G
a)4
b)3
c)2
d)1
e)0
 [Question 1316] A factory owner is going to construct a sales

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!

Q: