Question: Question 1 ( 3 + 4 + 4 + 3 = 1 4 points ) Consider the following process. The processing time ( sec /

Question 1(3+4+4+3=14 points)
Consider the following process. The processing time (sec/unit) is given for each worker.
Designed CT for Stage 140 sec / unit
Designed CT for Stage 2140 sec / unit
Bottleneck Stage: _2____
Process Designed CT 180 sec / unit
Process Capacity 22.5 units / hour
a) Calculate the following design parameters for this process:
b) Customers arrive at this process in the following way: Every 240 secs two customers arrives at M1 starting from time 0 and every 240 secs one customer arrives starting from time 100. Once a customer arrives at stage 2, if both servers are empty, the customer is served at the server with lower processing time. Fill in the below Gantt chart.
Each grid in the following chart represents 20 sec. You can extend the below chart as needed.
c) Under the arrival schedule given in (b), calculate the following run-time parameters:
Demand Rate 90 units/hour
Flow Rate units/hour
Actual Cycle Time sec/unit
WIP for Buffer 1 units
WIP for M1 units
WIP for Buffer 2 units
WIP for M2 units
WIP for M3 units
Total WIP units
Flow time secs
d) Use the total WIP and the flow time calculated in (c), then apply the Littles formula to get the flow rate and the actual CT. Specifically, show that
a. The flow rate calculated using the Littles law is the same as the flow rate calculated in (c) using the Gantt chart.
b. The actual CT calculated using the Littles law is the same as the actual CT calculated in (c) using the Gantt chart.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!