Question: QUESTION 1 3 8 points The Grand Performance Hall is in the process of remodeling and is scheduled to open for business after being closed
QUESTION
points
The Grand Performance Hall is in the process of remodeling and is scheduled to open for business after being closed for years. As part of the remodeling, it is installing a new sound system. The sound system is to be installed by Sound Systems, Inc. on or before April Opening night of the hall is May The contract states that "time is of the essence" because of the openingnight deadline. Sound Systems has some financial difficulties and doesn't deliver the system until April Grand Hall refuses to accept it and Sound Systems sues. What will be the result? Explain.