Question 13CLO #6: Develop a Preliminary (conceptual) Cost Estimate for a Commercial BuildingCLO #7: Develop a Preliminary (conceptual) Schedule for a Commercial BuildingWhat is the status of a project with negative cost variance and positive schedule variance?
A.Over budget - Behind schedule
B. Over budget - Ahead of schedule
C. Under budget - Ahead of schedule
D. Under budget - Behind schedule