Question: Question 1 (3 points) An operation analyst at the ABC is assigned to the team that is developing the process design. The corporate planning group

Question 1 (3 points) An operation analyst at the ABC is assigned to the team that is developing the process design. The corporate planning group has contacted her and asked how confident the design group is completing the project in 50 days. She has developed the following estimated time durations in days for the project assuming activity time is normally distributed and independent.

Activity

Immediate Predecessor

Activities

Optimistic

Time (to)

Most Likely Time (tm)

Pessimistic

Time (tp)

A

6

12

18

B

A

9

10

14

C

B

6

12

18

D

B

7

9

14

E

C, D

4

9

12

a. Compute the expected time and variance for each activity. (1 point)

b. Determine the critical path and expected duration of the project. (1 point)

c. What is the probability that the project will complete the project in 50 days? (1 point)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!