Question: Question 1 3 pts is a mathematical calculation and process which distributes the limited craft population by day to reduce the impact of craft -
Question
pts
is a mathematical calculation and process which distributes the limited craft population by day to reduce the impact of craftforce constraints on the project duration.
Resource Allocation
Resource Leveling
Schedule Crashing
Optimizing the Schedule