Question: Question 1 3 Your customer has decided that you cannot go forward with the project you're managing without a change to the agreed - upon

Question 13
Your customer has decided that you cannot go forward with the project you're managing without a change to the agreed-
upon WBS. A contract amendment is agreed on and signed, the change control system processes are followed, and you
modify the appropriate planning documents to reflect the change. As a result of the approved change, substantial
updates to the project costs and the project schedule occur as well. Which of the following is not true regarding this
situation? (PMB: Project Management Baseline)
Baselines must be adjusted to reflect the new project costs and schedule.
The PMB is determined using EVM.
The schedule, scope, and cost baseline together make up the PMB.
The PMB includes management reserves and contingencies.
Question 14
In what type of organizational structure do project managers have the most authority?
Circular
Functional
Project
Matrix

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!