Question: Question 1 4 1 pts In a manufacturing process, Actual Flow Time is calculated by: Adding both processing and waiting times from start to finish

Question 14
1 pts
In a manufacturing process, Actual Flow Time is calculated by:
Adding both processing and waiting times from start to finish
Adding up only the processing times for each step
Dividing the theoretical flow time by the total number of units
Subtracting waiting time from the total actual time spent in the process