Question: Question 1 ( 5 0 Points ) : Five work packages are assigned to a concreting crew. Takeoff quantity ( CY ) , percent waste,

Question 1(50 Points):
Five work packages are assigned to a concreting crew. Takeoff quantity (CY), percent waste, and
efficiency factor are estimated for each work package as shown in the table below. Technology
constrained precedence relationships are as: "Foundation" must be completed before executing
"Wall to Elevation" and "Slab"; all "Beams Elevated" must follow pouring "Wall to Elevation".
This crew has crew hourly rate of $370 per hour; crew hourly production under normal
circumstances (efficiency factor 1.0) is 12 CY per hour. The concrete unit cost is $30.90 per CY
delivered to site. This concreting crew handles one work package at a time. (CY=Cubic Yard)
Estimate total labor (crew) cost for the five work packages (rounding to $0.01).
Estimate total material cost for the five work packages (rounding to $0.01).
Estimate total crew hours required to complete the five work packages (rounding to 0.1
hr ).
Question 1 ( 5 0 Points ) : Five work packages

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!