Your project SPI is 0.86, and the management has recommended that you should fast track the project. You agree with the management, but caution them that fasttracking could:
Facilitate duration compression
Increase risk
Ensure activities are done in parallel, which would normally be done in sequence
Help shorten the project schedule without changing the project scope