Question: Question 1 5 3 pts The current customer demand for new mattresses is 2 0 0 per day. We currently work one 8 hour shift

Question 15
3 pts
The current customer demand for new mattresses is 200 per day. We currently work one 8 hour shift with 7.5 real work hours after breaks and produce 300 mattresses per day. What is the takt time of the process in minutes?
Greater than 3.5
Greater than or equal to 2.3 but less than 3
Less than 2.3
Greater than or equal to 3 but less than 3.5
 Question 15 3 pts The current customer demand for new mattresses