Johnson Controls has a project with a cost of $7,000 and expected cash flow stream of $2,000 at the end of year 1,$3,000 at the end of year 2, and $5,000 at the end of year 3. At a discount rate (WACC) of 10.88%, what is the net present value (NPV) of this investment?
Your answer should be between 580.00 and 1342.00, rounded to 2 decimal places, with no special characters.