Question: Question 1 (5) There are two basic methods of wage payment: (1) Hourly wages and (2) Piecework pay. Give five examples where piecework pay is
Question 1 (5)
There are two basic methods of wage payment: (1) Hourly wages and (2) Piecework pay. Give five examples where piecework pay is more suitable.
Question 2 (10)
Calculate the earnings of workers A and B under Piecework Pay and Taylors Differential Piecework system from the following:
Standard time allowed 50 units per hour.
Normal time rate per hour R100.
Differential to be applied:
80% of Piecework rate below standard.
120% of Piecework rate at or above standard.
In a day of 8 hours A produced 300 units and B produced 450 units.
Question 3 (15)
He keeps record of all jobs done at his workshop and provides you with the following records for Job 600 carried out in February 2006
| Direct materials issued | Direct labour | ||
| 01/02/2006 | R 2 500 | Skilled labour: | |
| 03/02/2006 | R 3 400 | 60 hours @ R150 per hour | |
| 09/02/2006 | R 4 100 | Semi-skilled labour: | |
| R10 000 | 45 hours @ R80 per hour | ||
Workshop overheads are absorbed at the rate of 80% o direct labour cost.
Job 600 was invoiced to the customer at a mark-up of 50% of the cost of production.
Required:
- Calculate the cost of Job 600.
- Show how the job was invoiced to the customer.