Question: Question 1 6 0 . 5 pts A project manager is using the Critical Path Method ( CPM ) to schedule a project. The following

Question 16
0.5 pts
A project manager is using the Critical Path Method (CPM) to schedule a project. The following table shows the activities, their durations, and immediate predecessors:
\table[[Activity,\table[[Duration],[(weeks)]],\table[[Immediate],[Predecessors]]],[A,3,A],[B,4,A],[C,2,B],[D,5,C],[E,3,D, E],[F,4,]]
What is the total project duration?
14 weeks
12 weeks
10 weeks
16 weeks