Question: Question 1 6 0 . 5 pts A project manager is using the Critical Path Method ( CPM ) to schedule a project. The following
Question
pts
A project manager is using the Critical Path Method CPM to schedule a project. The following table shows the activities, their durations, and immediate predecessors:
tableActivitytableDurationweekstableImmediatePredecessorsAABACBDCED EF
What is the total project duration?
weeks
weeks
weeks
weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
