Question: Question 1 6 ( 1 point ) Saved A network consists of the activities in the following list. table [ [ Activity , Predecessor

Question 16(1 point)
Saved
A network consists of the activities in the following list.
\table[[Activity,Predecessor Time],[A,---,6],[B,A,3],[C,A,13],[D,-cdots,4],[E,B,6],[F,D,2],[G,B,8],[H,C, E,3],[I,F, G,11],[J,H, I,7]]
Find the latest start time (LS) of activity E.