Question: Question 1 6 3 pts table [ [ Activity , table [ [ Optimistic Time ] , [ ( Weeks ) ] ]

Question 16
3 pts
\table[[Activity,\table[[Optimistic Time],[(Weeks)]],\table[[Most Likely Time (],[weeks)]],\table[[Pessimistic Time],[(weeks)]]],[A,8,10,12],[B,4,10,16],[C,4,5,6],[D,6,8,10],[E,4,7,12],[F,6,7,9],[G,4,8,12],[H,3,3,3]]
What is the Expected Project Completion Time for the AON and table above?
38.17
39
32.5
33.33
 Question 16 3 pts \table[[Activity,\table[[Optimistic Time],[(Weeks)]],\table[[Most Likely Time (],[weeks)]],\table[[Pessimistic Time],[(weeks)]]],[A,8,10,12],[B,4,10,16],[C,4,5,6],[D,6,8,10],[E,4,7,12],[F,6,7,9],[G,4,8,12],[H,3,3,3]] What