Question: Question ( 1 ) [ 6 Marks ] Your Plant is operating in batch mode, Calculate the batch cycle time and number of batch per

Question (1)[6 Marks]
Your Plant is operating in batch mode, Calculate the batch cycle time and number of batch per day through drawing the Gantt Chart: a) Sequential production schedule, b) Overlapping batches.
Table 1 Batch Data
\table[[Step,Duration (h)],[Drying,0.75],[Reaction,3],[Evaporation,0.75],[Distillation,6]]