Question: Question 1 7 ( 1 point ) When flyover bridge estimates were requested, the contractor gave pessimistic, optimistic, and most likely estimates considering the traffic
Question point
When flyover bridge estimates were requested, the contractor gave pessimistic,
optimistic, and most likely estimates considering the traffic and weather situations
which tool is being used in this scenario?
Bottomup estimating
Analogous estimating
Expert judgment
Parametric estimating
Threepoint estimates