Question: Question 1 7 ( 1 point ) When flyover bridge estimates were requested, the contractor gave pessimistic, optimistic, and most likely estimates considering the traffic

Question 17(1 point)
When flyover bridge estimates were requested, the contractor gave pessimistic,
optimistic, and most likely estimates considering the traffic and weather situations -
which tool is being used in this scenario?
Bottom-up estimating
Analogous estimating
Expert judgment
Parametric estimating
Three-point estimates