Question: Question 1 7 ( 4 points ) Contingency costs in the project costs estimate, also referred to as , are to cover unexpected situations that
Question points
Contingency costs in the project costs estimate, also referred to as are to cover unexpected situations that may come up during the project, such as items that may have been overlooked when the initial project scope was defined, activities that may have to be redone because they may not work the first time redesigns or a high probability or high impact risk that may occur.
auxiliary funds
reserves
withholding
capital funds
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
